Required Inspections

What about inspections?

The permit holder needs to call for inspections at specific times during the construction. We require a minimum of 72 hours notice on all inspections. The following are the inspections that are required in North Ogden City.

  • Sewer and Water: When the lines are installed from the road to the structure before the excavation is covered
  • Footing: When excavation is complete, the forms and reinforcement steel are in place but before any concrete is poured
  • Foundation: When forms and reinforcing steel are in place, but before any concrete is poured
  • Underground Plumbing: When underground plumbing and heating is in place but before the pipes are buried and the floor slab is poured
  • 4-way: When the wiring, plumbing and heating are installed and the framing is complete.  4-way inspection includes the following:
    • Framing: When all roof, walls, floor framing, fire stopping, and bracing are complete
    • Electrical: Rough wiring: Before any part of the work is concealed
    • Plumbing Inspection: Rough plumbing: Before any part of the work is concealed
    • Heating and Refrigeration Inspection: Rough heating and refrigeration: Before any part of the work is concealed
  • Power to Panel: Electrical meter is placed and ready to be hooked up
  • Flashing: Before or after the 4-way; before any brick or stucco is installed on a foundation ledge
  • Final Inspection: When all work is completed and prior to the home being occupied

Should you have any questions regarding these inspections, you may contact our Building Department at 801-737-9837.