Major Project: Randall Reservoir/Water Tank

Project Type:
Water
Project Status: 
Approved and Under Construction
Location: 
Reservoir
1300 East 2100 North
North Ogden , UT 84414

The Randall Reservoir project scope is to demolish the existing 500,000-gallon water storage reservoir tank and replace it with a 2,000,000-gallon water storage reservoir tank.  The reservoir will be fully enclosed concrete and conventional rebar reinforced concrete cylinder, with a 24-foot tall wall, from top to bottom.

The schedule (weather permitting) is as follows:

RANDALL TANK SCHEDULE

  • FORM BASE OF TANK 9/5/2023
  • TIE REBAR BASE 9/5/2023 -9/18/2023
  • SEET WATERSTOP, SCREEDS 9/19/2023
  • POUR BASE 9/20/2023
  • SET INSIDE FORMS WALLS 9/21/2023 – 9/25/2023
  • TIE WALL REBAR 9/25/2023 – 10/2/2023
  • FORM OUTSIDE WALL 10/3/2023 -10/5/2023
  • POUR WALLS 10/6/2023
  • STRIP INSIDE WALL FORMS 10/9/2023 – 10/11/2023
  • STRIP OUTSIDE WALL FORMS 10/12/2023 – 10/13/2023
  • POUR COLUMNS 10/6/2023 – 10/11/2023
  • SHORING 10/11/2023 – 10/25/2023
  • TIE REBAR ROOF 10/25/2023 – 11/9/2023
  • POUR LID 11/13/2023
  • TEAR OUT SHORING 11/20/2023 – 11/27/2023
  • CLEAN TANK 11/27/2023 – 12/1/2023
  • FILL TANK 12/1/2023 – 12/8/2023
  • BACKFILL WEATHER PERMITTING 12/12/2023

Projected project cost estimate: $2,200,000 

Subgrade
Gravel
Liner
Roadbase